This facility injects CO2 for enhanced oil recovery (EOR) in low permeability reservoirs of the Jilin oil field in northeast China. The CO2 is captured from a nearby natural gas processing plant at the Changling gas field, and transported by pipeline. After 12 years of pilot and demonstration tests, the commercial operation, as Phase III, began in 2018, reaching 600,000 tonnes CO2 per annum. Cumulative CO2 injection of 1.12 million tonnes for pilot and demonstration scale operation was reached in the 2017.

Project data is current as at 11/08/2018